We have also finalised plans for the
construction of another new hospital
project, KPJ BDC Specialist Hospital in
Kuching, Sarawak, on a total land area
of 4.74 acres. The approved development
budget for the project is RM100.0
million, with the contract awarded to
the Main Contractor amounting to
RM89 million.
The hospital will offer 300 beds, of
which 150 beds and a 107,000 sq ft car
park will be built under Phase 1 of the
project. The project commenced in
January 2016 and scheduled for
completion in 2017.
During the year, two of KPJ’s new
hospitals namely KPJ Pahang and KPJ
Perlis Specialist Hospital to reschedule
their openings due to contractor delays.
The projects are being managed closely
by KPJ’s Project Management team and
are now back on track. Management is
confident that these hospitals will be
completed soon and open their doors to
the public in 2016.
NEW HOSPITAL PROJECTS
In the year under review, we finalised
plans for the construction of a new
hospital, KPJ Miri Specialist Hospital in
Sarawak on a total land area of 4.0
acres. Phase 1 of the project is expected
to cost RM91.0 million to build.
According to the Master Plan, the
development of the hospital will provide
capacity for 180 beds in total, of which
96 beds (61 fitted; 35 vacant) and open
parking will be build under Phase 1.
Construction is scheduled to commence
in March 2016, with the duration of the
project scheduled for 16 months. Upon
the finalisation of contract amount
estimated at RM77.5 million subject to
approval of building plan from the
authorities and MOH.